In Dushanbe, as part of the implementation of the General Plan of the capital, construction and reconstruction work is underway, in particular, a new road has been built connecting Bukhoro and Khabibullo Nazarov streets, the press service of the Ministry of Transport of Tajikistan reports.
Construction and reconstruction work on the new road began on April 19, 2023. The road is 560 meters long, 16 meters wide, with four traffic lanes in two directions.
During the inspection, the Chairman of Dushanbe City Rustami Emomali was informed that during the implementation of the project of this facility, construction and installation works of utility networks, such as drinking water pipes, irrigation canals, high-voltage cables, hot water pipes, communication lines and outdoor lighting, were fully completed.
In addition, to ensure the safety of vehicle and pedestrian traffic during construction and reconstruction, guide lights and road safety sign elements have been fully installed.
Once fully operational, it will reduce traffic congestion on nearby roads and serve as an alternative route for vehicles.